HAUL ROAD | CIVIL WORKS
During the January school holidays, we installed a temporary haul road to access the back of a primary school, enabling asbestos removal, demolition, and relocations.
The road, approximately 110 meters long, was constructed to endure the weight and frequency of crane operations, anticipating over a year of use with continuous maintenance.
This essential infrastructure ensured the safe and efficient execution of the project and was completed in a two-week
timeframe.